Profiling Event Logs to Configure Risk Indicators for Process Delays

Abstract: Abstract. Risk identification is one of the most challenging stages in the risk management process. Conventional risk management approaches provide little guidance and companies often rely on the knowledge of experts for risk identification. In this paper we demonstrate how risk indicators can be used to predict process delays via a method for configuring so-called Process Risk Indicators (PRIs). The method learns suitable configurations from past process behaviour recorded in event logs. To validate the appro… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

0
14
0

Year Published

2014
2014
2018
2018

Publication Types

Select...
5
1

Relationship

1
5

Authors

Journals

citations
Cited by 20 publications
(14 citation statements)
references
References 17 publications
0
14
0
Order By: Relevance
“…For time series comparison we use R's wilcox method 11 that implements the Mann-Whitney U-test [7] and for trend fitting we use R's lm method 12 . The results of the analysis are visualised using the JFreeChart library 13 . Fig.…”
Section: Methodsmentioning
confidence: 99%
See 1 more Smart Citation
“…For time series comparison we use R's wilcox method 11 that implements the Mann-Whitney U-test [7] and for trend fitting we use R's lm method 12 . The results of the analysis are visualised using the JFreeChart library 13 . Fig.…”
Section: Methodsmentioning
confidence: 99%
“…In our own earlier work, we showed how process risk indicators can be used to detect the risk of case delays [12,13]. Some of these previous risk indicators were related to the behaviour of resources.…”
Section: Related and Previous Workmentioning
confidence: 99%
“…waiting for the assigned developer(s) to take actions. Abnormal waiting time is an indication of an issue being delayed due to lack of team cooperation or nobody wanting to deal with the issue [12]. The waiting time of an issue is from when an assignee has been assigned to the issue, until they take an action to resolve it such as changing the issue's status or submitting a pull request.…”
Section: B Potential Risk Factors For Software Issuesmentioning
confidence: 99%
“…A lack of resource planning has implications to project failures [21], and developer workload may have significant impact on the progress of a project [12,22]. A developer's workload is determined by the number of opened issues that have been assigned to the developer at a time.…”
Section: ) Changing Of Descriptionmentioning
confidence: 99%
See 1 more Smart Citation