A Novel Resource-Leveling Approach for Construction Project Based on Differential Evolution

Abstract: In construction engineering, project schedules are commonly established by the critical path method. Nevertheless, these schedules often lead to substantial fluctuations in the resource profile that are not only impractical but also costly for the contractors to execute. Therefore, in order to smooth out the resource profile, construction managers need to perform resource-leveling procedures. This paper proposes a novel approach for resource leveling, named as resource leveling based on differential evolution … Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1
1
1

Citation Types

0
7
0
1

Year Published

2014
2014
2022
2022

Publication Types

Select...
5
1

Relationship

2
4

Authors

Journals

citations
Cited by 10 publications
(8 citation statements)
references
References 22 publications
(27 reference statements)
0
7
0
1
Order By: Relevance
“…It is observable that the DeLOCP with the mutation strategy of DE/Target-to-Best/1 and Hybrid DE/Rand/1 and DE/Best/1 have produced the best solution: fitness function = 3054 (with average labor demand = 13.8, maximum labor demand = 16.0, minimum labor demand = 12, and project duration = 32.0 (shift)). The optimized crew sizes and start times of all activities are [13,7,4,9,6,4,6,7,8,8,13] and [1,2,2,6,14,9,9,25,27,17,32], respectively. The optimized daily labor demand is illustrated in Figure 4.…”
Section: Resultsmentioning
confidence: 99%
See 2 more Smart Citations
“…It is observable that the DeLOCP with the mutation strategy of DE/Target-to-Best/1 and Hybrid DE/Rand/1 and DE/Best/1 have produced the best solution: fitness function = 3054 (with average labor demand = 13.8, maximum labor demand = 16.0, minimum labor demand = 12, and project duration = 32.0 (shift)). The optimized crew sizes and start times of all activities are [13,7,4,9,6,4,6,7,8,8,13] and [1,2,2,6,14,9,9,25,27,17,32], respectively. The optimized daily labor demand is illustrated in Figure 4.…”
Section: Resultsmentioning
confidence: 99%
“…In most practical situations, project resources are available in certain quantities and a fluctuated resource profile is proved to be very costly for the contractors [6,9]. Thus far, the most challenging problem in project planning is to achieve an optimal project execution which results in an appropriate resource utilization with fixed duration.…”
Section: Introductionmentioning
confidence: 99%
See 1 more Smart Citation
“…In addition to the available algorithms for constructing and optimizing the calendar plans, mainly considered in the works of foreign authors [1][2][3][4][5][6][7][8][9][10], this article proposes a two-stage instrument that allows the General Contractor Organization to first isolate the permissible amount of work for transfer to the subcontractor balance, and then proceed to the formation of a calendar plan and resource schedules (Fig. 3).…”
Section: Fig 1 Scheme Of Production Planningmentioning
confidence: 99%
“…These two terms, trial vector and child vector, can be used interchangeably. This selection process is performed via selection between the parent and the corresponding offspring [25,26].…”
Section: Differential Evolution the Differential Evolution (De)mentioning
confidence: 99%