Project execution obstacles: a case of King Abdulaziz Airport in Saudi Arabia

Abstract: The purpose of this research is to examine the causes of delay in airport projects in general and the King Abdulaziz International Airport (KAIA) of Saudi Arabia in particular. The KAIA is the most strategic and busiest airport of Saudi Arabia, which transports millions of pilgrims from two hundred countries to perform Hajj and Umrah in Makkah. In general, more than 50% of construction projects fail on one more area. Our method of research is empirical based on the analysis of responses received from seventy-o… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1
1

Citation Types

0
4
0

Year Published

2021
2021
2024
2024

Publication Types

Select...
5

Relationship

0
5

Authors

Journals

citations
Cited by 5 publications
(4 citation statements)
references
References 15 publications
0
4
0
Order By: Relevance
“…The hazards associated with expanding projects are mainly unavoidable, although they are occasionally preventable. There are significant challenges that contribute to project delays in airport expansion projects as well as other building projects (Al Hudhaif, 2021). These are administrative challenges, hasty decision-making and planning, drawing preparation and approval, manpower shortage, and a lack of command and control.…”
Section: Literature Reviewmentioning
confidence: 99%
“…The hazards associated with expanding projects are mainly unavoidable, although they are occasionally preventable. There are significant challenges that contribute to project delays in airport expansion projects as well as other building projects (Al Hudhaif, 2021). These are administrative challenges, hasty decision-making and planning, drawing preparation and approval, manpower shortage, and a lack of command and control.…”
Section: Literature Reviewmentioning
confidence: 99%
“…In summary, the suggested conceptual framework was confirmed, and the analysis clarified the understanding of the current situation of project management standard practices and construction industry practitioners' awareness of the factors contributing to project success. Another research paper with the following topic "Project execution obstacles: a case of King Abdulaziz Airport in Saudi Arabia" (Hudhaif, 2021). The objective of this study was to identify the causes of the various delays in airport projects in Saudi Arabia, especially the King Abdulaziz International airport (KAIA).…”
Section: Literature Review On Pmo Importance and Project Success Factorsmentioning
confidence: 99%
“…To test the hypothesized relationships, this study relies on survey data collected from the plastics manufacturing sector in KSA. This particular sector provides a suitable context for addressing the research objectives of this study because organizations in this sector have adopted CT into their operations and processes, keeping in line with Saudi Arabia's National Vision 2030, where the digital transformation of industries is a key component (Al‐Maliki, 2021; Haines, 2021; Hudhaif, 2021). Moreover, the government of KSA is encouraging and assisting other organizations in the same sector that are yet to adopt CT in their processes to make the journey toward a more digitalized I4.0 environment (AlArjani et al, 2021; Atif, 2023).…”
Section: Introductionmentioning
confidence: 99%