“…"(1, 2, 5, 7))" "4 − 6""Inspection" "( (13,15,17,20), " " (11,15,18,19))" "5 − 6""Trail run" "((5, 7, 9, 15), " "(6, 10, 12, 14))" Hence the minimum completion duration of the intuitionistic fuzzy project duration is ((29,37,42,50), (22.5,26.5,29.5,31.5)) intuitionistic fuzzy months and ( (19,33,45,63); (16,25,32,38)) is the Jayagowri and Geetha Ramani's minimum completion duration of the project network for this same problem.…”