Impact of Information and Communication Technology Limitations on Microgrid Operation

Abstract: This paper provides an extensive review of the conducted research regarding various microgrids (MGs) control techniques and the impact of Information Communication Technology (ICT) degradation on MGs performance and control. Additionally, this paper sheds the light on the research gaps and challenges that are to be explored regarding ICT intrinsic-limitations impact on MGs operations and enhancing MGs control. Based on this assessment, it offers future prospects regarding the impact of ICT latencies on MGs and… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1
1
1

Citation Types

0
25
0

Year Published

2019
2019
2024
2024

Publication Types

Select...
6
3
1

Relationship

0
10

Authors

Journals

citations
Cited by 51 publications
(25 citation statements)
references
References 77 publications
0
25
0
Order By: Relevance
“…The main challenge of this transition process is to maintain the voltage and frequency levels within the predefined limits of grid standards [39,40]. Generally, for an islanded system, the inverter power output moves along the droop curve, and the setpoint of frequency f 0 depends on the SOC of the Energy Storage System (ESS) in the system.…”
Section: Transition From Grid-connected To Standalone Modementioning
confidence: 99%
“…The main challenge of this transition process is to maintain the voltage and frequency levels within the predefined limits of grid standards [39,40]. Generally, for an islanded system, the inverter power output moves along the droop curve, and the setpoint of frequency f 0 depends on the SOC of the Energy Storage System (ESS) in the system.…”
Section: Transition From Grid-connected To Standalone Modementioning
confidence: 99%
“…It could be seen that the uses of cross or strategy. The delay time τ of 300 ms, which could be considered as the worst case of communication delay [34], is used in this study. Table 2.…”
Section: B Large Wind Farm Systemmentioning
confidence: 99%
“…Modified mains protection devices may be required within a section of a microgrid, along with specific neutral grounding arrangements in mains isolation. Adequate communication infrastructure may also be required along with power lines [16]. In general, utility will have to modify their grid development practices where microgrids are expected to form.…”
Section: F Specific Regulation Regarding Intentional Islanding For Mmentioning
confidence: 99%