Causes of Delay in Khuzestan Steel Company Construction Projects

Abstract: Construction project is a competitive business with high risk especially in developing countries like Iran which faces with many problems such as delay and time and costs increases. Thus, the first priority here is to determine the causes of prolongation of construction projects and to evaluate their importance. Khuzestan Steel Company (KSC) has made important contribution to the projects in Iran and in turn is required to finish them on time. In this study, an attempt was made to investigate the causes of del… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

0
7
0

Year Published

2018
2018
2023
2023

Publication Types

Select...
7

Relationship

0
7

Authors

Journals

citations
Cited by 7 publications
(7 citation statements)
references
References 19 publications
0
7
0
Order By: Relevance
“…Iran: (1) projects for government [35]; (2) Khuzestan steel company [36] (1) The percentage of delay in 2001, 2002 and 2003 were respectively 30%, 74.5% and 75%. [35]; (2) the project duration is approximately 150% of project estimated duration [36].…”
Section: Delay Cases Reported In the Literature Evidence Of Delay In mentioning
confidence: 99%
“…Iran: (1) projects for government [35]; (2) Khuzestan steel company [36] (1) The percentage of delay in 2001, 2002 and 2003 were respectively 30%, 74.5% and 75%. [35]; (2) the project duration is approximately 150% of project estimated duration [36].…”
Section: Delay Cases Reported In the Literature Evidence Of Delay In mentioning
confidence: 99%
“…From a managerial viewpoint, in Brazil, Brazil, [13] noted that the top four factors affecting CTO were linked to labor such as rework, low labor productivity, lack of skilled labor, and their low qualification. Changes in price and inflation were the top ranked factor resulting from this study [40]. Furthermore, in contrast to major construction firms in developing countries, there is dominant and increasing business failure in construction due to various issues such as financial challenges.…”
Section: Factors Of Construction Time Overrun In Developing Countriesmentioning
confidence: 80%
“…The change of order was the top cause of delay in a study conducted in Taiwan which was based on the application of the RII [22]. Multiple studies have been done on the Iranian region in terms of causes and delay [23][24][25][26][27][28]. Other similar studies were conducted in Ghana [29,30], South Africa [31][32][33], Singapore [34,35] and Palestine [36,37], Libya [38], Nigeria [39][40][41], India [42][43][44], Taiwan [45,46], UAE [47], Egypt [48][49][50][51], Oman [52], Pakistan [53][54][55][56], Malawi [57], Zambia [58], Jordan [59], Malaysia [60][61][62][63], Turkey [64][65][66], Syria [67], Vietnam [68], Kenya…”
Section: Literature Reviewmentioning
confidence: 99%