2020
DOI: 10.14807/ijmp.v11i4.1065
|View full text |Cite
|
Sign up to set email alerts
|

Assessment of delay and cost-overrun in federal road construction project in Abuja

Abstract: Poor road infrastructure in Nigeria is a significant challenge, just like poverty, insecurity, and unemployment. The construction of road in the country is characterized by numerous challenges throughout the project life cycle. Some of these challenges are project delay and cost overrun, corruption and fraud, faulty contractual process among others. Objectives of this study are to identify factors influencing delays and cost overruns in road construction project, to rank these factors base on their impacts and… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1

Citation Types

2
1
0

Year Published

2021
2021
2024
2024

Publication Types

Select...
2
1

Relationship

0
3

Authors

Journals

citations
Cited by 3 publications
(3 citation statements)
references
References 19 publications
(7 reference statements)
2
1
0
Order By: Relevance
“…The construction delay risks related to material is in line with previous studies (Zhang et al 2020;Egila et al 2020;Durdyev and Hosseini, 2019;Abdullah and Alshibani, 2018;Rao et al 2016;Iqbal et al 2015). The PTFI's crusher system main materials are specific, big size and heavy.…”
Section: Methodssupporting
confidence: 85%
See 2 more Smart Citations
“…The construction delay risks related to material is in line with previous studies (Zhang et al 2020;Egila et al 2020;Durdyev and Hosseini, 2019;Abdullah and Alshibani, 2018;Rao et al 2016;Iqbal et al 2015). The PTFI's crusher system main materials are specific, big size and heavy.…”
Section: Methodssupporting
confidence: 85%
“…The construction delay risks related to resources is in line with previous studies (Egila et al 2020;Zhang et al 2020;Durdyev and Hosseini, 2019;Derakhsanfar et al 2019;Zidane and Andersen, 2018;Iqbal et al 2015). Construction of the crusher system was carried out using PTFI's own resources.…”
Section: Resourcessupporting
confidence: 76%
See 1 more Smart Citation