2014
DOI: 10.1680/geng.13.00035
|View full text |Cite
|
Sign up to set email alerts
|

Application of observational method at Crossrail Tottenham Court Road station, UK

Abstract: Excavation of the western ticket hall box at Tottenham Court Road station represented a critical path activity of the Crossrail railway project in London, UK. Base slab construction and preparatory sprayed concrete lining works needed to be completed before the arrival of the two tunnel boring machines. A full observational method (OM) design was implemented to eliminate the lowest level of temporary propping, resulting in a 13 m prop-free excavation at the bottom of the 30 m deep diaphragm wall station box. T… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1

Citation Types

0
8
0

Year Published

2014
2014
2024
2024

Publication Types

Select...
8
1

Relationship

1
8

Authors

Journals

citations
Cited by 13 publications
(8 citation statements)
references
References 1 publication
0
8
0
Order By: Relevance
“…The value engineering re-design of the temporary propping using the observational method (Nicholson et al, 1999) and the successful excavation of the western ticket hall have already been documented in some detail (Yeow et al, 2014). This acclaimed piece of engineering delivered savings of around £5 million and 6 weeks on the programme.…”
Section: Designmentioning
confidence: 98%
“…The value engineering re-design of the temporary propping using the observational method (Nicholson et al, 1999) and the successful excavation of the western ticket hall have already been documented in some detail (Yeow et al, 2014). This acclaimed piece of engineering delivered savings of around £5 million and 6 weeks on the programme.…”
Section: Designmentioning
confidence: 98%
“…Despite not previously being formally defined, approach C has been the most commonly adopted. The Crossrail case history at Tottenham Court Road western ticket hall (Chen et al, 2015;Yeow et al, 2014) is a recent example.…”
Section: Choice Between Approaches a And B For Ab Initiomentioning
confidence: 99%
“…Figure 2 TCR-WTH layout plan and section (Bologna, 2017, Yeow, 2014 To minimize the excavation duration, the observational method was adopted to modify the design during construction, allowing the lowest level of temporary props to be omitted. This reduced costs and saved about four weeks on the programme.…”
Section: String Length L(b)mentioning
confidence: 99%