Approx. 42 km of tunnel were excavated on the contract Tulfes‐Pfons H33, including a 15 km long section of the exploratory tunnel, which has been excavated since October 2015 with a gripper TBM from the Ahrental access tunnel southward into the district of Steinach. The interaction of the tunnel boring machine with the rock mass is discussed here as a back analysis of the mechanized tunnelling drive. This article does compare the forecast with the actual geological/geotechnical conditions, but only considers the conditions actually encountered. The back analysis takes place analogously to the principle of geotechnical planning according to the ÖGG (Austrian Society of Geomechanics) guideline, in which, starting from the rock mass structure and the rock mass types, the encountered tunnel face and intrados behaviour are observed and an estimation of the system behaviour is carried out. A description of the tunnelling technology concept completes this paper together with two case studies and the lessons learned.
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.