2021
DOI: 10.1016/j.tust.2020.103650
|View full text |Cite
|
Sign up to set email alerts
|

Vertical tunneling in China-A case study of a hydraulic tunnel in Beihai

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
3
2

Citation Types

0
22
0

Year Published

2021
2021
2024
2024

Publication Types

Select...
6

Relationship

3
3

Authors

Journals

citations
Cited by 12 publications
(22 citation statements)
references
References 16 publications
0
22
0
Order By: Relevance
“…To deal with the sewage from the sewage treatment plant in Beihai, China, the VTM was used to construct vertical standpipes in the sea area, together with the pipe jacking method [1][2][3]. The horizontal tunnel was built by the pipe jacking method firstly, and the diameter was 2000 mm.…”
Section: Construction Processmentioning
confidence: 99%
See 4 more Smart Citations
“…To deal with the sewage from the sewage treatment plant in Beihai, China, the VTM was used to construct vertical standpipes in the sea area, together with the pipe jacking method [1][2][3]. The horizontal tunnel was built by the pipe jacking method firstly, and the diameter was 2000 mm.…”
Section: Construction Processmentioning
confidence: 99%
“…Figure 3 shows the construction flow chart of the VTM. Wang et al depicted a detailed description of the VTM, comprising the construction process [3]. Before the VTM construction started, the soil above the excavation line was excavated.…”
Section: Construction Processmentioning
confidence: 99%
See 3 more Smart Citations