2016 57th International Scientific Conference on Power and Electrical Engineering of Riga Technical University (RTUCON) 2016
DOI: 10.1109/rtucon.2016.7763081
|View full text |Cite
|
Sign up to set email alerts
|

Towards optimization of combined cycle power plants' start-ups and shut-down

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
3
1
1

Citation Types

0
12
0

Year Published

2017
2017
2022
2022

Publication Types

Select...
4
3

Relationship

2
5

Authors

Journals

citations
Cited by 15 publications
(12 citation statements)
references
References 6 publications
0
12
0
Order By: Relevance
“…The equations (1-9) of the EM (Table 1) are developed based on information in Fig. 2 and previously obtained knowledge about transient modes and characteristic properties of combined cycle gas turbine technology in [24,25]. /h] The natural gas consumption for electricity production in periods is:…”
Section: Development Of the Evaluation Modelmentioning
confidence: 99%
“…The equations (1-9) of the EM (Table 1) are developed based on information in Fig. 2 and previously obtained knowledge about transient modes and characteristic properties of combined cycle gas turbine technology in [24,25]. /h] The natural gas consumption for electricity production in periods is:…”
Section: Development Of the Evaluation Modelmentioning
confidence: 99%
“…Power supply of gas metering station is provided from substation "Iecava" through two 110 kV transmission lines and, respectively, through the 20 kV network. Reservation of power supply can be implemented through 20 kV network, and additional autonomous diesel generators are installed in the gas metering station [6], [7], [11], [14], [22].…”
Section: Critical Infrastructurementioning
confidence: 99%
“…In Latvia, natural gas is mainly used for producing electricity and heat. In order to encourage the diversification of natural gas supply paths and sources as well as the emergence of a natural gas market, BEMIP states a list of the required infrastructure entities, which foresees the construction of the Gas Interconnector Poland-Lithuania as well as the improvement of the Latvia-Lithuania and Latvia-Estonia interconnections and the modernization and enlargement of Incukalns underground gas storage, which will increase the natural gas supply reliability and stability in the region [3], [11]- [14].…”
Section: Introductionmentioning