The Successful Design, Construction and Commissioning of A 11 L/S (0.25-MGD) Biological Nutrient Removal PILOT Plant in Ten Months

Abstract: The Advanced Treatment Technology Pilot (ATTP) project provides a valuable example for successfully implementing a fast-paced project to demonstrate compliance with stringent nutrient removal and tertiary treatment permit requirements. The ATTP project was designed, built and commissioned in ten months on schedule, on budget, with no injuries, and at a construction cost of $12 million. This paper contains a description of how the selection of a design, build, own, and operate (DBOO) delivery implementation ben… Show more