The space-borne INTEGRAL-SPI gamma ray telescope: test and calibration campaigns

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
2
1

Citation Types

0
5
0

Year Published

2002
2002
2006
2006

Publication Types

Select...
4
1

Relationship

3
2

Authors

Journals

citations
Cited by 9 publications
(5 citation statements)
references
References 5 publications
0
5
0
Order By: Relevance
“…The interactions between the Ge-camera, ACS, PSD and DFEE (Schanne et al 2002) were adjusted as during on-ground tests (Schanne et al 2003).…”
Section: Internal Timing Performancementioning
confidence: 99%
See 1 more Smart Citation
“…The interactions between the Ge-camera, ACS, PSD and DFEE (Schanne et al 2002) were adjusted as during on-ground tests (Schanne et al 2003).…”
Section: Internal Timing Performancementioning
confidence: 99%
“…The SPI-system level tuning-phase took place during the PV-phase. The interactions between the Ge-camera, ACS, PSD and DFEE (Schanne et Al. 2002) were adjusted as during on-ground tests (Schanne et al 2003).…”
Section: Internal Timing Performancementioning
confidence: 99%
“…In April 2001, day and night during one month, SPI was calibrated at CEA in Bruyères le Châtel [5] (see Fig. 9).…”
Section: The Spi Ground Calibrationmentioning
confidence: 99%
“…For example using a 60 Co source, the measured 1332 keV peak showed a full width at half maximum (FWHM) between 2.1 and 2.6 keV for all 19 detectors over a large temperature range, confirming that a good energy resolution is expected in flight in case of low radiation damages or after annealing. During the month of April 2001 the SPI on-ground calibration campaign [10][11] took place at CEA in Bruyères le Châtel (France). In May 2001 the spectrometer was delivered to ESA and was integrated on board of the satellite at Alenia in Torino (Italy).…”
Section: Integration and Test Campaigns Of Spimentioning
confidence: 99%
“…The SPI on-ground calibration campaign [10] was performed during the whole month of April 2001 at the CEA center of Bruyères le Châtel (France). This site was selected since it offered the possibility for the manipulation of high activity radioactive sources as well as the use and modification of its accelerator complex.…”
Section: On-ground Calibration Of Spimentioning
confidence: 99%