Icptt 2011 2011
DOI: 10.1061/41202(423)204
|View full text |Cite
|
Sign up to set email alerts
|

Study on Thrust of Earth-Pressure-Balanced Shield Tunneling in Gravel

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1

Citation Types

0
2
0

Year Published

2013
2013
2024
2024

Publication Types

Select...
1
1

Relationship

0
2

Authors

Journals

citations
Cited by 2 publications
(2 citation statements)
references
References 0 publications
0
2
0
Order By: Relevance
“…In order to study the degree of influence of construction of electric shield tunneling under the Ba River on geological and ground deformation, and to analyze the sensitivity of various construction parameter factors to the geological environment, three influencing factors were selected: soil chamber pressure, grouting pressure, and grouting layer thickness [7,8] , with four different levels for each factor. According to the actual engineering situation, the L16 (43) orthogonal test table was selected to simulate 16 working conditions [9] .…”
Section: Design and Results Analysis Of Orthogonal Experimental Numer...mentioning
confidence: 99%
“…In order to study the degree of influence of construction of electric shield tunneling under the Ba River on geological and ground deformation, and to analyze the sensitivity of various construction parameter factors to the geological environment, three influencing factors were selected: soil chamber pressure, grouting pressure, and grouting layer thickness [7,8] , with four different levels for each factor. According to the actual engineering situation, the L16 (43) orthogonal test table was selected to simulate 16 working conditions [9] .…”
Section: Design and Results Analysis Of Orthogonal Experimental Numer...mentioning
confidence: 99%
“…Construction cycle: The simulation of gravity stress field → soil excavation, releasing part of the hole circumferential stress→ segment on the excavated section at the same time release the rest hole circumferential stress→ next soil excavation, releasing part of the hole circumferential stress→ segment on the excavated section at the same time release the rest hole circumferential stress. The rest of the excavations are of the same steps[2][3]. Formation parameters refer to engineering geology exploration report of the preliminary design stage as shown in Table1.…”
mentioning
confidence: 99%