Settlement of Surrounding Grounds Due to Existence of Pile Pulling-Out Holes

Abstract: The demolition of social infrastructures including the civil structures have been increasing because of aging them constructed during in a period of high economic growth and decrease in their utilization with a population decrease, in recent years. As a result, removal works of existing pile in the ground have been increasing. Pulling-out method is adopted for removal of existing a pile foundation in the present circumstances. However, after pulling-out a pipe foundation, decline of mechanical characteristic o… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1

Citation Types

0
3
0

Year Published

2020
2020
2024
2024

Publication Types

Select...
6

Relationship

3
3

Authors

Journals

citations
Cited by 10 publications
(3 citation statements)
references
References 0 publications
0
3
0
Order By: Relevance
“…1). A two-dimensional elastic analysis by the FEM was carried out on a ground from which the existing piles had not been pulled out, on a ground from which the existing piles had been pulled out and the pullout holes had been left hollow, and on a ground from which the existing piles had been pulled out and the pullout holes had been filled with a filler [9]. However, an analysis in two dimensions can only account for the displacement on the X-Y plane.…”
Section: Pulling-out Analysis Of Piles In Two Dimensionsmentioning
confidence: 99%
See 1 more Smart Citation
“…1). A two-dimensional elastic analysis by the FEM was carried out on a ground from which the existing piles had not been pulled out, on a ground from which the existing piles had been pulled out and the pullout holes had been left hollow, and on a ground from which the existing piles had been pulled out and the pullout holes had been filled with a filler [9]. However, an analysis in two dimensions can only account for the displacement on the X-Y plane.…”
Section: Pulling-out Analysis Of Piles In Two Dimensionsmentioning
confidence: 99%
“…In this method, the casing hugs and pulls out the entire existing piles. With this method, therefore, it is possible to more reliably pull out broken existing piles and existing piles whose joint parts are not joined than with other pullingout methods [9,10].…”
Section: Introductionmentioning
confidence: 99%
“…Therefore, problems arise when parts of existing piles are left in the ground after the pulling-out process. The pile tip chucking method [6,7] is a pulling method that was developed to solve these problems. In this method, the entire length of an existing pile is wrapped and pulled up and out of the ground by the casing.…”
Section: Introductionmentioning