2008
DOI: 10.1016/j.tust.2008.01.002
|View full text |Cite
|
Sign up to set email alerts
|

Safe rapid drifting – Support selection

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

0
8
0
1

Year Published

2009
2009
2024
2024

Publication Types

Select...
8

Relationship

0
8

Authors

Journals

citations
Cited by 12 publications
(9 citation statements)
references
References 13 publications
0
8
0
1
Order By: Relevance
“…This technique involves an excavation or work cycle comprising a number of different activities. Suorineni et al [3] mention the following unit operations: drilling of the tunnel surface, loading of explosives and blasting, ventilation (considered as an interference within the cycle), scaling and loading of the blasted material, and fortification (bolts, nets, and shotcrete, among others). Figure 1 illustrates the drilling and blasting cycles involved in tunneling.…”
Section: Tunnel Constructionmentioning
confidence: 99%
See 1 more Smart Citation
“…This technique involves an excavation or work cycle comprising a number of different activities. Suorineni et al [3] mention the following unit operations: drilling of the tunnel surface, loading of explosives and blasting, ventilation (considered as an interference within the cycle), scaling and loading of the blasted material, and fortification (bolts, nets, and shotcrete, among others). Figure 1 illustrates the drilling and blasting cycles involved in tunneling.…”
Section: Tunnel Constructionmentioning
confidence: 99%
“…In the first loop, there is the variable "operation," whose purpose is to identify the operations that will be performed in the third loop and that are adapted according to the operations of the construction cycle described by Suorineni et al [3]. It should be noted that this is the only alphanumeric variable.…”
Section: Control Of the Number Of Simulationsmentioning
confidence: 99%
“…Therefore, blast-induced damage is not accounted for in the modified Q 0 in Equation (1). Suorineni et al [55] argue that excavation-induced damage in rock masses should be taken into account in estimating rock mass quality for support selection. This argument is supported by Løset [52] and Hoek et al [56].…”
Section: Blasting Effectsmentioning
confidence: 99%
“…There are many factors affecting construction time of a drill and blast tunnel (Chen and Liu, 2007;Palmstrom and Brock, 2006;Suorineni et al, 2008;Zare and Bruland, 2007). Hence, it is very difficult to predict and analyze how much each factor influences the total construction time, even though it is important for efficient work scheduling.…”
Section: Introductionmentioning
confidence: 99%