Proceedings of the 2013 International Symposium on Slope Stability in Open Pit Mining and Civil Engineering 2013
DOI: 10.36487/acg_rep/1308_69_degraaf
|View full text |Cite
|
Sign up to set email alerts
|

Risk management and remediation of the north wall slip, West Angelas Mine, Western Australia

Abstract: A planar failure of approximately 600 kT occurred on the north wall of Centre Pit North (CEPN) at West Angelas Mine site in February 2010. The failure impacted a substantial resource of high grade iron ore and left a number of significant geotechnical hazards on and adjacent to the failure surface. These presented a series of challenges which had to be overcome in order to remediate the failure and reclaim the bulk of the buried ore. A number of recovery options were investigated and presented to management. T… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...

Citation Types

0
1
0

Year Published

2013
2013
2020
2020

Publication Types

Select...
2
1

Relationship

1
2

Authors

Journals

citations
Cited by 3 publications
(1 citation statement)
references
References 0 publications
0
1
0
Order By: Relevance
“…This enables automated acquisition of data and also links to the Geoscience Monitoring Data System (GMDS). TDRs were installed as part of the remediation plan of a significant instability at one of the Pilbara operations (Joass et al, 2013).…”
mentioning
confidence: 99%
“…This enables automated acquisition of data and also links to the Geoscience Monitoring Data System (GMDS). TDRs were installed as part of the remediation plan of a significant instability at one of the Pilbara operations (Joass et al, 2013).…”
mentioning