Project Scheduling Analysis Using the Precedence Diagram Method (PDM) Case Study: Surabaya’s City Outer East Ring Road Construction Project (Segment 1)

Abstract: The project acceleration by the Crash Program is one of the ways that is often used to make time and cost efficiency on an ongoing project. Acceleration of project completion time will affect the efficiency of equipment and labor productivity. In the case study of the Surabaya Outer East Ring Road Project Construction Segment 1, a project that has the potential to be accelerated is discussed in order to obtain efficiency values in terms of time and cost, Project acceleration by means of the Crash Program using… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1
1
1

Citation Types

0
8
0

Year Published

2021
2021
2024
2024

Publication Types

Select...
7

Relationship

0
7

Authors

Journals

citations
Cited by 8 publications
(9 citation statements)
references
References 0 publications
0
8
0
Order By: Relevance
“…The aggregate used in this study came from the Keude Linteng stone cruiser, Nagan Regency. The Australian Asphalt Pavement Association (2004) explains that the asphalt content for aggregates with a maximum size of 14 mm can use an asphalt content of 4.5% -6% of the total mixture to determine the value of the Optimum Asphalt Content (KAO) [2]. There are 4 asphalt content selected for the manufacture of the test object, namely: 4.5%; 5%; 5.5% and 6% of the total weight of the mixture as much as 1100 gr.…”
Section: Methodsmentioning
confidence: 99%
See 1 more Smart Citation
“…The aggregate used in this study came from the Keude Linteng stone cruiser, Nagan Regency. The Australian Asphalt Pavement Association (2004) explains that the asphalt content for aggregates with a maximum size of 14 mm can use an asphalt content of 4.5% -6% of the total mixture to determine the value of the Optimum Asphalt Content (KAO) [2]. There are 4 asphalt content selected for the manufacture of the test object, namely: 4.5%; 5%; 5.5% and 6% of the total weight of the mixture as much as 1100 gr.…”
Section: Methodsmentioning
confidence: 99%
“…However, it is inversely proportional to the supply of asphalt itself, this is because asphalt is a non-renewable material. To anticipate the supply of asphalt, innovations or research on asphalt is needed [2]. The combination of 25% CPO and 75% Asphalt Pen 60/70 has been carried out for the AC-WC mixture.…”
Section: Introductionmentioning
confidence: 99%
“…Films made from cellulose derivatives and a number of thermoplastic resins in the form of sheets and tubes can be used as wrappers, bags and covers [5]. Films from a mixture of starch and plasticizers can be used as packaging, but must meet certain mechanical properties [6].…”
Section: Literature Reviewmentioning
confidence: 99%
“…Compensation given is in the form of money, material facilities, and career opportunities [13]. f. Job Design Defines job design as the process of determining the tasks to be performed, the methods used to carry out these tasks, and how the work is related with other jobs in the organization [14].…”
Section: Physical Condition Of Workmentioning
confidence: 99%