Proactive Project Scheduling With Activity Splitting and Resource Transfer Times Under Uncertain Environments

Abstract: Proactive project scheduling aims to generate robust baseline schedules that are protected against the potential schedule disruptions during project execution. In this paper, we propose a new problem named the proactive resource-constrained project scheduling problem with activity split-ting and resource transfer times, and try to investigate the trade-off between the benefits of activity splitting and the drawbacks of the resulting more resource transfer times. The proposed problem is formulated into an integ… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1

Citation Types

0
1
0

Year Published

2024
2024
2024
2024

Publication Types

Select...
2

Relationship

0
2

Authors

Journals

citations
Cited by 2 publications
(1 citation statement)
references
References 43 publications
0
1
0
Order By: Relevance
“…Project scheduling, as an important component of project management, can provide scientific decision-making support for project managers [1]. The resource-constrained project scheduling problem (RCPSP) studies the reasonable scheduling of the start time of all activities while satisfying the priority relationship constraints between activities and resource constraints to achieve the goals of project managers, such as minimizing project completion time or cost [2]- [4]. With the development of the global economy and the intensification of market competition, the scale and quantity of projects that enterprises need to manage simultaneously have also increased.…”
Section: Introductionmentioning
confidence: 99%
“…Project scheduling, as an important component of project management, can provide scientific decision-making support for project managers [1]. The resource-constrained project scheduling problem (RCPSP) studies the reasonable scheduling of the start time of all activities while satisfying the priority relationship constraints between activities and resource constraints to achieve the goals of project managers, such as minimizing project completion time or cost [2]- [4]. With the development of the global economy and the intensification of market competition, the scale and quantity of projects that enterprises need to manage simultaneously have also increased.…”
Section: Introductionmentioning
confidence: 99%