Ore Composition’s Impact on Smelting Profitability: An Optimum Pricing Index Model for Long-Term Nickel Ore Feedstock Purchasing Agreements

Abstract: Global Nickel (Ni) smelters’ have been experiencing profit losses for nearly a decade due to the 2008 recession still impacting the industry, oversupply, and fluctuating ore quality. This paper proposes to aid the Ni smelters with the lattermost issue, presenting an optimum pricing index model for purchasing raw Ni ore materials. The model is developed using data from a major Ni smelter in operation in Korea, including parameters such as revenues, investment expenses, and ore purchasing costs and the impact Ni… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1

Citation Types

0
2
0

Year Published

2019
2019
2022
2022

Publication Types

Select...
3

Relationship

1
2

Authors

Journals

citations
Cited by 3 publications
(2 citation statements)
references
References 37 publications
0
2
0
Order By: Relevance
“…The impact of changing the risk ownership structure of a steel plant project through a tolling agreement will be different than other sectors. There have been publications dedicated to solving the economic pressures felt by steel producing companies including optimal risk-assessment processes [28], optimal investment timing [29], risk-sharing feedstock agreements [30], and creating financing [31] but minimal on the impact of differing SPC agreements. The lack of publications on the tolling agreement's use on steel projects represents a gap in the literature.…”
Section: Sponsor Project Company Sponsor Tolling Companymentioning
confidence: 99%
“…The impact of changing the risk ownership structure of a steel plant project through a tolling agreement will be different than other sectors. There have been publications dedicated to solving the economic pressures felt by steel producing companies including optimal risk-assessment processes [28], optimal investment timing [29], risk-sharing feedstock agreements [30], and creating financing [31] but minimal on the impact of differing SPC agreements. The lack of publications on the tolling agreement's use on steel projects represents a gap in the literature.…”
Section: Sponsor Project Company Sponsor Tolling Companymentioning
confidence: 99%
“…Realyvásquez-Vargas, et al [6] apply the plan-do-check-act (PDCA) cycle to identify the sources of defects and reduce the proportion of the defects by up to 65%, integrating tools such as the Pareto diagram and flow chart. In turn, Jeong, et al [7] propose a purchase price index model for South Korean nickel smelters integrating variables such as revenue, investment expenses, and material purchase costs, and the findings indicate that the risk of quality fluctuation is mitigated.…”
mentioning
confidence: 99%