New Technologies to Enhance Performance of Section Milling Operations that Reduces Rig Time for P&A Campaign in Norway

Abstract: In 2008, ConocoPhillips completed the plug and abandonment (P&A) of two of eight water injection wells at the 2/4 W Platform in the Norwegian sector of the North Sea. The average performance was 65 days per well. One of the most challenging aspects of the 2008 P&A campaign was deep section milling of the casing to install the secondary reservoir barrier where multiple section mill runs were necessary. In mid-2009 ConocoPhillips resumed operations to P&A the remaining 6 wells. The scope to P&A the remaining 6 w… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2

Citation Types

0
2
0

Year Published

2016
2016
2022
2022

Publication Types

Select...
3
2

Relationship

0
5

Authors

Journals

citations
Cited by 6 publications
(2 citation statements)
references
References 0 publications
0
2
0
Order By: Relevance
“…Under such circumstances the casing needs to be milled, swarf has to be removed and the remaining casing pulled. These procedures are very time consuming and thus very expensive [2]. Data from ConocoPhillips [2] indicate that pipe removal is one of the most time-consuming P&A operations, taking on average 65 days [2].…”
Section: Introductionmentioning
confidence: 99%
See 1 more Smart Citation
“…Under such circumstances the casing needs to be milled, swarf has to be removed and the remaining casing pulled. These procedures are very time consuming and thus very expensive [2]. Data from ConocoPhillips [2] indicate that pipe removal is one of the most time-consuming P&A operations, taking on average 65 days [2].…”
Section: Introductionmentioning
confidence: 99%
“…These procedures are very time consuming and thus very expensive [2]. Data from ConocoPhillips [2] indicate that pipe removal is one of the most time-consuming P&A operations, taking on average 65 days [2]. Assuming a daily rig day of USD 0.47 million [3] pipe removal from only one well can cost on average USD 38 million.…”
Section: Introductionmentioning
confidence: 99%