Minimizing earthwork volumes by optimizing vertical alignment with linear programming algorithm

Abstract: Earthwork cost is one of the major cost items (approximately 25% of the construction costs) in road construction projects. The amount of earthwork volumes therefore earthwork cost, mostly depends on the geometry of the road vertical alignment. We can conclude that an optimized vertical alignment has a profound impact on earthwork costs. In this research paper, we solve the task connected to the minimization of earthwork cost by optimizing vertical alignment by the development of linear optimization model with … Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1

Citation Types

0
1
0
1

Year Published

2021
2021
2023
2023

Publication Types

Select...
5

Relationship

0
5

Authors

Journals

citations
Cited by 5 publications
(2 citation statements)
references
References 16 publications
(19 reference statements)
0
1
0
1
Order By: Relevance
“…Earthwork operations are an integral part of many medium and large construction projects. For instance, more than 20% of the total cost of road projects is dedicated to earthwork operations (Artun et al , 2019; Parente et al , 2015; Hare et al , 2011; Smith et al , 1996). These operations are complex and dynamic in nature, and there are many different factors that need to be monitored closely to ensure the success of a project (Cheng et al , 2011).…”
Section: Introductionmentioning
confidence: 99%
“…Earthwork operations are an integral part of many medium and large construction projects. For instance, more than 20% of the total cost of road projects is dedicated to earthwork operations (Artun et al , 2019; Parente et al , 2015; Hare et al , 2011; Smith et al , 1996). These operations are complex and dynamic in nature, and there are many different factors that need to be monitored closely to ensure the success of a project (Cheng et al , 2011).…”
Section: Introductionmentioning
confidence: 99%
“…6 видно, что БЛ, формируемые алгоритмом, не всегда являются плавными. Но, в то же время, сгладить БЛ методами, предложенными в[4][5][6], не представляется возможным, так как в указанных работах один числовой ряд, а в данной статье обработке должны подвергаться несколько взаимосвязанных рядов. Для подбора оптимального коэффициента сглаживания каждой БЛ в отдельности и их соотношения между собой необходимо затратить большое количество…”
unclassified