2011
DOI: 10.1061/(asce)sc.1943-5576.0000071
|View full text |Cite
|
Sign up to set email alerts
|

Lezkairu Utilities Tunnel

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
3
1

Citation Types

0
3
0

Year Published

2020
2020
2023
2023

Publication Types

Select...
8

Relationship

0
8

Authors

Journals

citations
Cited by 10 publications
(4 citation statements)
references
References 0 publications
0
3
0
Order By: Relevance
“…The process of MUT construction using this method includes (1) surveying; (2) demolition of urban furniture; (3) excavation of the surface for diverting the current utilities; (4) diversion of the old utilities that already exist in the location; (5) trench excavation; (6) assembly of the trench shoring system; (7) preparation of the bed for placing the precast concrete sections; (8) delivery of the precast concrete sections to the construction site; (9) attaching the sections to the crane and lifting them; (10) placement of the sections; (11) sealing the joint between sections; (12) installation of the required supports (e.g., trays and hangers) for the utility systems; (13) installation of the utilities; ( 14) displacement of the trench shoring system; (15) backfilling; (16) installation of the MUT's own networks (e.g., security cameras, fire detectors, etc. ); and (17) pavement restoration.…”
Section: Candc Simulation Modelmentioning
confidence: 99%
See 1 more Smart Citation
“…The process of MUT construction using this method includes (1) surveying; (2) demolition of urban furniture; (3) excavation of the surface for diverting the current utilities; (4) diversion of the old utilities that already exist in the location; (5) trench excavation; (6) assembly of the trench shoring system; (7) preparation of the bed for placing the precast concrete sections; (8) delivery of the precast concrete sections to the construction site; (9) attaching the sections to the crane and lifting them; (10) placement of the sections; (11) sealing the joint between sections; (12) installation of the required supports (e.g., trays and hangers) for the utility systems; (13) installation of the utilities; ( 14) displacement of the trench shoring system; (15) backfilling; (16) installation of the MUT's own networks (e.g., security cameras, fire detectors, etc. ); and (17) pavement restoration.…”
Section: Candc Simulation Modelmentioning
confidence: 99%
“…MUT construction methods can be classified into two main groups: cut-and-cover (C&C) methods [14,15] and trenchless methods [16]. Despite the high initial cost of the trenchless methods, avoiding the excavation of roads and low social costs make these methods more appealing.…”
Section: Introductionmentioning
confidence: 99%
“…The construction of utility tunnels has undergone development for over 100 years, leading to the emergence of two main construction methods: cast-in-place (CIP) concrete and prefabricated concrete [6][7][8]. While CIP utility tunnels offer high flexibility in execution, their application often necessitates extensive formwork, resulting in time-consuming processes due to concrete hardening.…”
Section: Introductionmentioning
confidence: 99%
“…Currently, researchers have analyzed the planning and design [12,13], construction [14][15][16], or O&M stage [17] of UUT projects. Several studies have attempted to solve certain challenges in construction and O&M. To ensure safety and sustainability in the O&M stage, scholars have proposed to avoid the risks in later operations by incorporating considerations at the UUT design stage [18]. Yet, these studies neglected the whole life cycle factors affecting UUT sustainability.…”
Section: Introductionmentioning
confidence: 99%