Abstract:Minimizing all waste (waste) is mandatory for the company. The results of the study using a lean approach, followed by looking at the winding process as a whole, Big Picture Mapping and identification of waste that occurs in business processes, carried out by comparing the actual time to the standard time for the winding process, the value-adding time for the winding process is 21310 minutes. In contrast, the total production time is about 22995 minutes. The non-value-addingtime ,whichdoes not add value… Show more
Set email alert for when this publication receives citations?
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.