Investigation of Contact Layer «Foundation Grill – Ground Base» Soil Structure Damage and Its Regeneration by Crimping

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
3
1

Citation Types

0
4
0

Year Published

2020
2020
2023
2023

Publication Types

Select...
4

Relationship

0
4

Authors

Journals

citations
Cited by 4 publications
(4 citation statements)
references
References 5 publications
0
4
0
Order By: Relevance
“…At object No. 1, at the first stage of work, in order to ensure the geometrically correct position of building structures and eliminate existing gaps in the "base -foundation" contact zone, injection was performed into this zone [7]. To prevent the exit of the mortar, metal profiled sheets were installed along the perimeter of the foundation slab (Fig.…”
Section: Methodsmentioning
confidence: 99%
“…At object No. 1, at the first stage of work, in order to ensure the geometrically correct position of building structures and eliminate existing gaps in the "base -foundation" contact zone, injection was performed into this zone [7]. To prevent the exit of the mortar, metal profiled sheets were installed along the perimeter of the foundation slab (Fig.…”
Section: Methodsmentioning
confidence: 99%
“…Reconstruction and major repairs of buildings and structures are carried out in order to eliminate their physical deterioration and provide their expansion or additional functional use; this is accompanied by strengthening or replacing the structural elements of the building, adding storeys, deepening basements and making basement storeys, interior redevelopment and modification. The result is as follows: foundation loading increases by 30 to 50% (Khomyakov et al 2017 [3], Mali and Singh 2018 [4], Samorodov 2018 [5], Stepanov et al 2018 [6]). Thus, pile foundations suffer from overloading and this results in the need to strengthen them by embedding extra piles or strengthening the soil bed.…”
Section: Introductionmentioning
confidence: 95%
“…At the same time, it is often assumed that unsuitable soil is excavated from the base and replaced with stronger, less compressible soils (often sandy), but any violation of the work technology (insufficient compaction of the backfill soil, non-compliance with the size of the soil fraction, the inclusion of frozen fractions, abundant soaking during the work, etc.) leads to a deterioration of the physical and mechanical characteristics of the soil of the filled artificial bases laid down by the project, which is usually detected already during operation, and it requires their further operational strengthening [5][6][7][8].…”
Section: Introductionmentioning
confidence: 99%
“…This method allows you to fill the pores that are present in the soil thickness, thereby reducing its compressibility, as well as increasing its strength characteristics. One of the methods of applying high-pressure injection is the crimping of the ground base and the restoration of the contact layer at the "foundation-base" boundary [5].…”
Section: Introductionmentioning