Integrated Activity Scheduling and Site Layout Planning

Abstract: -A temporal-spatial scheduling model is used to consider the location and movement of equipment, material and temporary structures on a construction site over time, ensuring efficient yet safe processes. The model ties together activity scheduling and dynamic site layout planning, fully integrating two domains that have so far been treated separately. Their integration is facilitated by modeling temporary site objects like cranes as singularity functions. These objects are explicitly linked in the model with w… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1

Citation Types

0
2
0

Year Published

2018
2018
2018
2018

Publication Types

Select...
2

Relationship

0
2

Authors

Journals

citations
Cited by 2 publications
(2 citation statements)
references
References 15 publications
0
2
0
Order By: Relevance
“…Prevailing activity-oriented construction scheduling techniques -e.g., Gantt Chart, Network Diagram, Critical Path Method-are not able to consider spatial requirements of activities and for this reason the generated construction schedule is limited in capturing real site conditions. Moreover, more complex techniques -such as Line of Balance-have likewise insufficient ability for workspaces planning because they assume that only one labor crew is able to occupy each work-zone at a time and they lack of a 3-Dimensional representation and planning of spaces as well as spatial conflicts among themselves [9].…”
Section: Need and Justificationmentioning
confidence: 99%
“…Prevailing activity-oriented construction scheduling techniques -e.g., Gantt Chart, Network Diagram, Critical Path Method-are not able to consider spatial requirements of activities and for this reason the generated construction schedule is limited in capturing real site conditions. Moreover, more complex techniques -such as Line of Balance-have likewise insufficient ability for workspaces planning because they assume that only one labor crew is able to occupy each work-zone at a time and they lack of a 3-Dimensional representation and planning of spaces as well as spatial conflicts among themselves [9].…”
Section: Need and Justificationmentioning
confidence: 99%
“…However, all these approaches tackle a unique aspect of the scheduling problem: CB is about optimal sequencing, GA on resource optimization and levelling, NN on time-cost tradeoff and optimization, MB on spatial reasoning. Some remarkable examples about MB simulated the construction process either by means of a set of differential equations [15], or an integrated mathematical model [16] or a probabilistic approach [17].…”
Section: Scientific Backgroundmentioning
confidence: 99%