Impact of Design Changes in Construction Project

Abstract: Design changes in construction projects are always going to happen and cannot be avoided. Design changes are the primary contributor to disruption of time and cost performance of construction projects. Previous research in this domain lacks of detail studies on systematic review on the existing literature. This paper reviewed literature published in peer-reviewed journals and conference proceedings in the construction management field and had emailed several questions to the expert in construction industry. Th… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
3
1
1

Citation Types

0
6
0

Year Published

2021
2021
2024
2024

Publication Types

Select...
3

Relationship

0
3

Authors

Journals

citations
Cited by 3 publications
(6 citation statements)
references
References 23 publications
(40 reference statements)
0
6
0
Order By: Relevance
“…Using the author's experience as an example of typical weighing judgment from an experienced civil engineer would likely take the last as the major cause of design changes. Though several papers [3], [4], [6] and [7] agree with the experience of the author, this paper intends to look at those causes without weighing any experience judgments by assuming all the sources above have the same risk potential.…”
Section: Perspective From Risk Managementmentioning
confidence: 83%
See 3 more Smart Citations
“…Using the author's experience as an example of typical weighing judgment from an experienced civil engineer would likely take the last as the major cause of design changes. Though several papers [3], [4], [6] and [7] agree with the experience of the author, this paper intends to look at those causes without weighing any experience judgments by assuming all the sources above have the same risk potential.…”
Section: Perspective From Risk Managementmentioning
confidence: 83%
“…Abou Chakra [5], in his paper presents estimations of cost overruns in several project categories due to design changes. The paper by Muhamad et al [6] seems to agree with Yana [3], arguing that overruns in construction projects are significantly instigated by the project owners. Shoar et al [7] presents a deeper analysis using an Interpretive Structural Modeling Approach on the design changes causes.…”
Section: Literature Reviewmentioning
confidence: 90%
See 2 more Smart Citations
“…Additionally, five factors common to all three groupings identified design change/error issues as common causes for delays. Changes in design ranked as the fifth leading cause for delays in building projects in Ghana out of the nine main factors identified for delays [30]. In another study, delay in completion schedule was the most visible effect of variation orders from all the viewpoints [18].…”
Section: Effects Of Design Changementioning
confidence: 99%