Fusion Technology 1994 1995
DOI: 10.1016/b978-0-444-82220-8.50059-5
|View full text |Cite
|
Sign up to set email alerts
|

Experimental Complex for High Flux-Materials Interaction Research

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1

Citation Types

0
3
0

Year Published

2000
2000
2015
2015

Publication Types

Select...
7
1

Relationship

1
7

Authors

Journals

citations
Cited by 11 publications
(3 citation statements)
references
References 1 publication
0
3
0
Order By: Relevance
“…Typical ITER-like ELM events deposit ∼3 MJ in 0.1-1 ms at the area of ~1 m 2 [29] with the corresponding heat flux factor of 30-300 MJ m −2 s −1/2 . The heat loads were performed by the electron beam 'Tsefey-M' facility (Efremov Institute) [48], producing e-beams with = P 195 e kW and 18 μs duration, which was enough to cause local tungsten melting. Electron beam treatment of the tungsten mock-ups resulted in melting of a surface layer, with cracks reaching a depth of 2.4 mm and in decreasing of the micro-hardness up to a depth of 4 mm.…”
Section: Investigation Of Tungsten Mock-up Tiles Interacting With Pla...mentioning
confidence: 99%
“…Typical ITER-like ELM events deposit ∼3 MJ in 0.1-1 ms at the area of ~1 m 2 [29] with the corresponding heat flux factor of 30-300 MJ m −2 s −1/2 . The heat loads were performed by the electron beam 'Tsefey-M' facility (Efremov Institute) [48], producing e-beams with = P 195 e kW and 18 μs duration, which was enough to cause local tungsten melting. Electron beam treatment of the tungsten mock-ups resulted in melting of a surface layer, with cracks reaching a depth of 2.4 mm and in decreasing of the micro-hardness up to a depth of 4 mm.…”
Section: Investigation Of Tungsten Mock-up Tiles Interacting With Pla...mentioning
confidence: 99%
“…in heating phase and 20 K/min. in cooling phase) is realized by an electron beam facility, TSEFEY, 16) Efremov Institute (Russia). Because of the short brazing time, formation of brittle intermetallic zone was considerably suppressed.…”
Section: Be Materials and The Componentsmentioning
confidence: 99%
“…To perform comprehensive testing of the divertor mock-ups two different types of heat loads need to be selected [7]. For simulation of nominal and transient regimes (q=1-20 MW/m2, 010 s) the TSEFEY, the electron beam facility operated for last 3 years is proposed.…”
Section: Facilitiesmentioning
confidence: 99%