Discussion. Construction of 60-In. - Dia. Outfall Sewer for Morecambe and Heysham Corporation.

Abstract: 315in progress, calling for either steam plant, compressors with their appropriate tools, pumps, etc.outputs On the, beach and gantry sections 164 pipes were laid in 129 working weeks. For most of the time two units of two or three gangs each were employed. The pipe laying varied from two per unit week t o one pipe in 4 weeks when conditions were bad.The number of unit weeks waa 224, giving an average of 0.73 pipes, or 18 f t 3 in. per week for each unit.The total cost of the work cannot be closely assessed un… Show more