Discovering the Impact of Late Change Orders and Rework on Labor Productivity: A Water Treatment Case Study Analysis Using System Dynamics Modeling

Abstract: Most complex projects can expect some level of rework and minor changes that can be conceptually predicted and estimated during the bidding process. However, existing literature and practitioners' experience indicate that the true impact of late change orders and rework on labor productivity behavior is often greater than expected, and the unintended side effects are very difficult to measure. This lack of knowledge and understanding leads to inaccurate calculations of the true impact of project changes and cr… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
3
1
1

Citation Types

0
20
0

Year Published

2019
2019
2023
2023

Publication Types

Select...
6
2
1

Relationship

2
7

Authors

Journals

citations
Cited by 26 publications
(26 citation statements)
references
References 18 publications
(23 reference statements)
0
20
0
Order By: Relevance
“…However, owing to the obscure nature of quality, it can hardly be defined and measured. Consequently, the two components of project time and cost overrun have been tied to the evaluation of construction projects' performance [3,4]. The project cost and time are important to the management team at all times [5,6].…”
Section: Introductionmentioning
confidence: 99%
“…However, owing to the obscure nature of quality, it can hardly be defined and measured. Consequently, the two components of project time and cost overrun have been tied to the evaluation of construction projects' performance [3,4]. The project cost and time are important to the management team at all times [5,6].…”
Section: Introductionmentioning
confidence: 99%
“…Highly Productive: The production of prefabricated components for modular construction is tightly controlled and mostly automated [33]. The laborers who produce the components are skillful if for no other reason than they repeatedly perform the same procedure [44,45]. In addition, the components are not subjected to weather conditions that might affect the quality of the materials [34].…”
Section: Advantagementioning
confidence: 99%
“…As "design changes and modifications" attribute to schedule delays in construction projects [38,39], it is very important to identify their root cause. The professionals who were involved in LCH projects stated that errors and omissions in the planning and specification stages are a key cause of reworks.…”
Section: Early Identification Of Errors In Planning and Specificationsmentioning
confidence: 99%