Developing labour productivity norms for aluminium system formwork in Sri Lanka

Abstract: Purpose -The purpose of this paper is to establish labour productivity norms (LPNs) on an elemental basis to investigate a measurement for the labour productivity (LP) of aluminium system formwork (ASF) in low-cost housing projects (LHPs) in Sri Lanka.Design / methodology / approach -Case study approach was selected as the most appropriate for the study and semi-structured interviews, document review and direct observations were used for the data collection. Four case studies were conducted. Eight semi-structu… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1

Citation Types

0
1
0

Year Published

2018
2018
2024
2024

Publication Types

Select...
5

Relationship

0
5

Authors

Journals

citations
Cited by 11 publications
(1 citation statement)
references
References 19 publications
0
1
0
Order By: Relevance
“…Data were collected by interviewing project managers and obtaining project documents, such as the schedule, the bill of quantities and the daily progress report. The activity crew productivity is calculated for the different combinations of execution modes (Senarath Jayasinghe and Fernando, 2017). Alongside, quality assessment was also carried out to compute the quality parameter.…”
Section: Identification Of Different Activity Execution Modesmentioning
confidence: 99%
“…Data were collected by interviewing project managers and obtaining project documents, such as the schedule, the bill of quantities and the daily progress report. The activity crew productivity is calculated for the different combinations of execution modes (Senarath Jayasinghe and Fernando, 2017). Alongside, quality assessment was also carried out to compute the quality parameter.…”
Section: Identification Of Different Activity Execution Modesmentioning
confidence: 99%