“…Based on the cost correlations of civil and electro-mechanical components, total SHP cost is given by C SHP = 1.13 (C CIV + C EM ), (16) where C CIV is the cost of civil works, C PHB is cost of powerhouse building, C DW&I is cost of diversion weir and intake, C PC is cost of power channel, C DC is cost of desilting chamber, C F&S is cost of forebay and spillway, C PST is cost of the penstock, C TR is cost of tailrace, C I is cost of intake, C S is cost of spillway, C DW is cost of diversion weir, C TG is cost of turbine governor system, C GE is cost of generator exciter system, C AUX is cost of mechanical and electrical auxiliaries, C T&SY is cost of transformer and switchyard, C EM is cost of electromechanical works and C SHP is cost of SHP plant. The factor 1.13 corresponds to establishment related costs including survey and investigations, preliminary expenses on report preparation, design, audit and accounting, overheads, tools and facilities, communication costs and land costs have been included in indirect/ miscellaneous costs [6,19,20,30].…”