Campos Basin: Lessons Learned and Critical Issues To Be Overcome in Drilling and Completion Operations

Abstract: Drilling and completion in Campos Basin have been in constant evolution, from the first subsea wells and fixed platforms to latest horizontal wells in deepwater. This paper will first present the lessons learned with drilling and completion in shallow water to latest wells drilled and completed in Roncador in the range of 1,800 meters of water depth. Exploratory drilling will be also addressed. The main points to be presented are: well design, horizontal and multi lateral wells, well head design, well control,… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1

Citation Types

0
2
0

Year Published

2007
2007
2017
2017

Publication Types

Select...
3
3

Relationship

0
6

Authors

Journals

citations
Cited by 10 publications
(2 citation statements)
references
References 0 publications
0
2
0
Order By: Relevance
“…The first successful subsea TCM operation was performed in April 1992 in a subsea production manifold flowline. After successive evolution steps, in March 1994 a new rigless procedure was introduced with huge operational cost reduction 8 .…”
Section: Organic Deposition In Deepwater Fields -A Step Change In Cammentioning
confidence: 99%
“…The first successful subsea TCM operation was performed in April 1992 in a subsea production manifold flowline. After successive evolution steps, in March 1994 a new rigless procedure was introduced with huge operational cost reduction 8 .…”
Section: Organic Deposition In Deepwater Fields -A Step Change In Cammentioning
confidence: 99%
“…Affected by the drilling vessel drifting and sea current beating and other issues, the riser would threaten the stability of subsea wellhead mechanics [4][5][6][7]. Recent years scholars have conducted relational studies such as riser stress state, the stability of subsea wellheads, the bearing capacity of casing string below the mud line, the setting depth of conductor and so on, they have drawn some valuable conclusions [8][9][10].…”