Assessment of Cause of Huluka Micro Hydro Power Scheme Failure and Estimation of Its Potential

Abstract: In Ethiopia, several Micro hydropower (MHP) schemes were constructed between the year 1950 and 1970. One of the Micro hydropower schemes constructed within this period was Huluka Micro-hydropower. However, it is no longer operational nowadays due to some issues and problems. Hence, this research study aimed to assess the causes of failure and estimating the potential power of Huluka micro hydropower. The overall existing condition of the components of the Micro hydropower plants evaluated as to functionality a… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...

Citation Types

0
0
0

Publication Types

Select...

Relationship

0
0

Authors

Journals

citations
Cited by 0 publications
references
References 2 publications
0
0
0
Order By: Relevance

No citations

Set email alert for when this publication receives citations?