Assessing the Exergy Costs of a 332-MW Pulverized Coal-Fired Boiler

Abstract: Abstract:In this paper, we analyze the exergy costs of a real large industrial boiler with the aim of improving efficiency. Specifically, the 350-MW front-fired, natural circulation, single reheat and balanced draft coal-fired boiler forms part of a 1050-MW conventional power plant located in Spain. We start with a diagram of the power plant, followed by a formulation of the exergy cost allocation problem to determine the exergy cost of the product of the boiler as a whole and the expenses of the individual co… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1
1

Citation Types

0
3
0

Year Published

2016
2016
2022
2022

Publication Types

Select...
4
1
1

Relationship

0
6

Authors

Journals

citations
Cited by 6 publications
(4 citation statements)
references
References 25 publications
0
3
0
Order By: Relevance
“…Using the method, the work potential and energy efficiency of the system can be calculated [18][19][20][21][22]. Therefore, it is widely used in power system design and boiler improvement [23][24][25][26][27]. Shi [28] determined the boiler efficiency from soot blowing and proposed a superior model to improve the boiler performance.…”
Section: Introductionmentioning
confidence: 99%
“…Using the method, the work potential and energy efficiency of the system can be calculated [18][19][20][21][22]. Therefore, it is widely used in power system design and boiler improvement [23][24][25][26][27]. Shi [28] determined the boiler efficiency from soot blowing and proposed a superior model to improve the boiler performance.…”
Section: Introductionmentioning
confidence: 99%
“…Abdelmotalib et al remarked that due to very complicated processes, which occur in the fluidized bed combustors, it is difficult to cover all aspects of heat transfer [ 9 ]. Therefore some additional, auxiliary data, e.g., to adjust parameters or to solve complex differential equations are necessary, and even other assumptions should be made to get a trackable solution [ 33 , 34 , 35 , 36 , 37 , 38 ]. As an example, Zhou et al pointed out that simulations conducted on the platform of FLUENT 12 software with three processors parallel for 70 s with the number of meshes nearly 8500 costs nearly 60 days [ 15 , 39 ].…”
Section: Introductionmentioning
confidence: 99%
“…There are some studies about coal-fired boilers [7][8][9][10]. Figure 1 shows a schematic of a coal-fired oxy-fuel boiler [11], in which oxygen is first separated from the air and then mixed with a stream of recycled flue gases from the boiler.…”
Section: Oxygen Combustion In the Coal-fired Boilermentioning