Application of Three Metaheuristic Algorithms to Time-Cost-Quality Trade-Off Project Scheduling Problem for Construction Projects Considering Time Value of Money

Abstract: Time, cost, and quality have been known as the project iron triangles and substantial factors in construction projects. Several studies have been conducted on time-cost-quality trade-off problems so far, however, none of them has considered the time value of money. In this paper, a multi-objective mathematical programming model is developed for time-cost-quality trade-off scheduling problems in construction projects considering the time value of money, since the time value of money, which is decreased during a… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1

Citation Types

0
3
0

Year Published

2022
2022
2024
2024

Publication Types

Select...
7

Relationship

1
6

Authors

Journals

citations
Cited by 15 publications
(3 citation statements)
references
References 57 publications
0
3
0
Order By: Relevance
“…The RAS equation is as follows (Jolai et al., 2013; Sadeghi et al ., 2023):In which Fi=min{f1i,f2i}. The less value the better (Jolai et al., 2013; Kebriyaii et al ., 2021).…”
Section: Computational Resultsmentioning
confidence: 99%
See 1 more Smart Citation
“…The RAS equation is as follows (Jolai et al., 2013; Sadeghi et al ., 2023):In which Fi=min{f1i,f2i}. The less value the better (Jolai et al., 2013; Kebriyaii et al ., 2021).…”
Section: Computational Resultsmentioning
confidence: 99%
“…In which F i ¼ minff 1i ; f 2i g. The less value the better (Jolai et al, 2013;Kebriyaii et al, 2021).…”
Section: The Algorithm Performance Criteriamentioning
confidence: 99%
“…Mahdiraji et al [25] proposed a new hesitant fuzzy TCQT model to identify the best implementation option for each project activity in an R&D real project in the food industry. Kebriyaii et al [26] concentrated on solution approaches and applied three metaheuristic algorithms in a TCQT problem, taking into account the time value of money for construction projects. Tao et al [27] proposed a stochastic programming model for TCT problems in the GERT-type network so as to minimize the mean duration within an appropriate on-time completion probability and under-budget probability.…”
Section: Introduction and Literature Reviewmentioning
confidence: 99%