2018
DOI: 10.1007/s10749-018-0898-0
|View full text |Cite
|
Sign up to set email alerts
|

Analysis of the Specifics of Selecting Relay Protection and Automatic (RPA) Equipment in Distributed Networks with Auxiliary Low-Power Generating Facilities

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

0
6
0

Year Published

2020
2020
2022
2022

Publication Types

Select...
6
1

Relationship

0
7

Authors

Journals

citations
Cited by 22 publications
(7 citation statements)
references
References 0 publications
0
6
0
Order By: Relevance
“…Voltage sag and interruption parameters largely depend on the PSP algorithms and configurations in the internal and external grid as well as on the switching units' opening times. Therefore, upgrading DVSCs to shorten SC elimination times can effectively minimize their characteristics [8,9]. Based on the above, DVRs and DVSCs are generally required to:  keep busbar voltage for critical loads within the required range during voltage sags and interruptions (limits on depth and duration application);  perform as required while using minimum ESS power and energy density, if any;  minimize active power loss in inverter converters and coupling transformers (if any) in normal operation (no SCs, no ARC or ALT-related dead times);  have minimum effect on the voltage/current harmonics and cos at the connection point;  maximize the specific apparent power (kVA/kg, kVA/m 3 ) and energy density for as much as the design allows;  be scalable, i.e., allow connecting additional ESS modules.…”
Section: Overview Of Solutions For Internal Gridsmentioning
confidence: 99%
“…Voltage sag and interruption parameters largely depend on the PSP algorithms and configurations in the internal and external grid as well as on the switching units' opening times. Therefore, upgrading DVSCs to shorten SC elimination times can effectively minimize their characteristics [8,9]. Based on the above, DVRs and DVSCs are generally required to:  keep busbar voltage for critical loads within the required range during voltage sags and interruptions (limits on depth and duration application);  perform as required while using minimum ESS power and energy density, if any;  minimize active power loss in inverter converters and coupling transformers (if any) in normal operation (no SCs, no ARC or ALT-related dead times);  have minimum effect on the voltage/current harmonics and cos at the connection point;  maximize the specific apparent power (kVA/kg, kVA/m 3 ) and energy density for as much as the design allows;  be scalable, i.e., allow connecting additional ESS modules.…”
Section: Overview Of Solutions For Internal Gridsmentioning
confidence: 99%
“…Empirical data suggests that reduction drives are associated with lower GTE reliability and longer repairs [4],  Phase loads are symmetrized, as synchronous generators are not able to sustain phase-asymmetric loads for long, and relay protection and automation (RPA) systems will disconnect the generator to prevent it from overheating and associated damage. This situation may arise when a DES-equipped area is islanded whilst still carrying a load [5][6][7],  Protections are less likely to initiate DES disconnection due to close SCs or voltage sags to below 0.8Unom for over 0.2 s, which would be critical for conventional GS's,  Input voltage amplitude, phase, and frequency can be controlled with a far shorter delay (≈ 1-3 ms) compared to conventional GS's, which enables the automatic control system (ACS) to run a variety of control algorithms:…”
Section: Benefits Of Inverter Gs'smentioning
confidence: 99%
“…Technical requirements for DERs and their connection to 6-35 kV grids with a capacity of 0.5-1 to 5 MW and those with a capacity of 5 to 25 MW should be drawn up with a similar gradation for photovoltaic, wind, and thermal power plants [13].…”
Section: Development Of Technical Requirements For Dersmentioning
confidence: 99%