Abstract:Surabaya–Gempol Toll Road is a toll that has operated since 1986, but in 2006 the Porong-Gempol route collapsed due to lapindo mud flow. Therefore, the toll road needs a relocation. On the construction of its relocation, additional scope of work was added and affected the feasibility of the investment which must be put into consideration for analyzing purposes in order to regain the initial feasibility value of 14.84% IRR. The forecast of cost and income analyzed with financial approach. The method used are Ne… Show more
Set email alert for when this publication receives citations?
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.