An Interval Programming Based Approach for fully uncertain Resource-Constrained Project Scheduling Problem Considering Project Manager’s Attitude toward Risk

Abstract: In recent years, there has been a growing attention to model and solve resource-constrained project scheduling problem (RCPSP) under uncertain environments. In most of the real-life cases, project managers may face with many uncertainties in activity durations, resource availabilities, resource requirements of the activities, the earliest and latest finishing times of the activities etc. In addition to these input parameters, project schedule which represents the starting and/or completion times of the activit… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
2
1

Citation Types

0
6
0

Year Published

2020
2020
2021
2021

Publication Types

Select...
3
1

Relationship

1
3

Authors

Journals

citations
Cited by 4 publications
(6 citation statements)
references
References 48 publications
0
6
0
Order By: Relevance
“…Because of these overlapped fuzzy numbers, precedence relations among the project activities may not be satisfied explicitly. This problematic issue has already mentioned by Subulan (2019Subulan ( & 2020 and defined as one of the risky situations in fully uncertain project scheduling applications. Actually, standard fuzzy arithmetic based solution approaches may cause these risky situations.…”
Section: Integer Linear Programming (Ilp) Model Formulation Of the Multi-objective Fs-mripspmentioning
confidence: 99%
See 4 more Smart Citations
“…Because of these overlapped fuzzy numbers, precedence relations among the project activities may not be satisfied explicitly. This problematic issue has already mentioned by Subulan (2019Subulan ( & 2020 and defined as one of the risky situations in fully uncertain project scheduling applications. Actually, standard fuzzy arithmetic based solution approaches may cause these risky situations.…”
Section: Integer Linear Programming (Ilp) Model Formulation Of the Multi-objective Fs-mripspmentioning
confidence: 99%
“…In this section, a literature survey on fuzzy-stochastic and fuzzy-random project scheduling problems is presented. In fact, researches in this field can be mainly classified into three parts, i.e., fuzzy, stochastic and fuzzy-random project scheduling problems according to the type of uncertainties (Subulan 2019;Subulan, 2020). Most of the previous researches handled the uncertain project parameters/input data by making use of probability or fuzzy set theories.…”
Section: A Literature Review On Fuzzy-stochastic Project Scheduling Problemsmentioning
confidence: 99%
See 3 more Smart Citations