Multi-stage dumping sequence - a feasible waste management alternative for open pit mining

Abstract: Waste management and environmental aspects are progressively gathering attention in the mining industry. Mine planners must deal with increasingly complex tasks to balance between ore block schedules, waste disposal, operational cost and environmental reclamation. The mine incomes are generally related to mining and processing of the ore, thus most optimization researches regarding strategic mining usually focus mainly on ore extraction. Nevertheless, waste sequencing and disposal play an important role given … Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
2
1

Citation Types

0
6
0

Year Published

2022
2022
2024
2024

Publication Types

Select...
5

Relationship

1
4

Authors

Journals

citations
Cited by 5 publications
(6 citation statements)
references
References 15 publications
0
6
0
Order By: Relevance
“…Each time a block is hauled, the cost is applied; thus re-handling operations represent an extra cost. Differently from previous work (Kuckartz and Peroni 2019;Kuckartz et al 2021Kuckartz et al , 2022, this case study does not consider equipment acquisition (such as haulage trucks and shovels), given that a contractor is responsible for managing a fleet capable of dealing with the mine schedule within the limits of material movement assumed in this analysis.…”
Section: Methodsmentioning
confidence: 99%
See 3 more Smart Citations
“…Each time a block is hauled, the cost is applied; thus re-handling operations represent an extra cost. Differently from previous work (Kuckartz and Peroni 2019;Kuckartz et al 2021Kuckartz et al , 2022, this case study does not consider equipment acquisition (such as haulage trucks and shovels), given that a contractor is responsible for managing a fleet capable of dealing with the mine schedule within the limits of material movement assumed in this analysis.…”
Section: Methodsmentioning
confidence: 99%
“…The data regarding waste block schedules, comprising the operational cost, waste dump capacities and haulage distances were compiled in a spreadsheet where the calculation was performed, including NPC at a 10% annual discounted rate. The findings of this study were also integrated with previous results from Kuckartz and Peroni (2019), Kuckartz et al (2021Kuckartz et al ( , 2022 and then synthesised to provide overall guidance for the potential use of the MSDS, listing the main variables and their relationships.…”
Section: Methodsmentioning
confidence: 99%
See 2 more Smart Citations
“…This article [17] investigates a new approach for mine waste management called the multi-stage dumping sequence, suggesting the use of temporary waste dumps along the way to the final dump destination. Although this method requires material re-handling, which is considered a paradigm in mine industry, it certainly provides additional time to design and permit the final waste dump site and, if well planned, might even result in profit increases by reducing haulage distances in the first years of operation.…”
Section: Introductionmentioning