Reliable Implementation of Robust Adaptive Topology Control

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
3
1
1

Citation Types

0
5
0

Year Published

2015
2015
2020
2020

Publication Types

Select...
5
1
1

Relationship

0
7

Authors

Journals

citations
Cited by 18 publications
(5 citation statements)
references
References 14 publications
0
5
0
Order By: Relevance
“…However, CSA is a selection algorithm that was only focussed on linearised DC model and user-specified line list; it did not consider all lines in the network. Robust adaptive topology control was thereafter suggested with some practical requirements for reliable implementation of the TLS, to identify lines that may be switched back to service after being tripped erroneously by a relay (Kezunovic et al , 2014). As a follow-up on the adaptive topology control, TLS is further applied to show line vulnerability and susceptance to outages during a sudden loss of transmission line (Okojie et al , 2015).…”
Section: Taxonomy Of Transmission Line Switchingmentioning
confidence: 99%
“…However, CSA is a selection algorithm that was only focussed on linearised DC model and user-specified line list; it did not consider all lines in the network. Robust adaptive topology control was thereafter suggested with some practical requirements for reliable implementation of the TLS, to identify lines that may be switched back to service after being tripped erroneously by a relay (Kezunovic et al , 2014). As a follow-up on the adaptive topology control, TLS is further applied to show line vulnerability and susceptance to outages during a sudden loss of transmission line (Okojie et al , 2015).…”
Section: Taxonomy Of Transmission Line Switchingmentioning
confidence: 99%
“…Under the normal assumption for both distributions prior and likelihood in (8), the explicit computation of variance is not necessary. Instead it is computationally favorable to compute the optimal trade-off parameter nu from the interval [0, 1].…”
Section: Data Analyticsmentioning
confidence: 99%
“…Transmission systems operators need to identify approximate locations of outages so that crews can be efficiently dispatched [7]. While the line outage is in effect, and crews are inspecting and repairing the damage, the operator may implement adequate switching actions to reduce the impact of the outage on the overall supply [8].…”
Section: Introductionmentioning
confidence: 99%
“…Practical implementation concerns and impacts on circuit breaker reliability are studied in [37]- [40]; AC formulation of topology control optimization is approached in [41], [42]; Out-of-market corrections of the AC infeasible market solutions for day-ahead accommodation of transmission line switching is investigated in [43], [44]. Scalability concerns of topology control implementations in real-world power systems are addressed in [19], [45]- [49].…”